N.C. 12 decision delayed for study of 7-mile bridge

NCDOT is looking at a 7-mile-long bridge around southern Pea Island, while rock and sheet piling is being installed to protect a temporary bridge.
full story »


More erosion control needed for temporary bridge

Rocks and walls will be added over the next four to six weeks to protect the southern landing of the temporary N.C. 12 bridge, requiring temporary lane closures.
full story »


State wants to expand emergency ferry terminals

State highway planners are looking for Dare County’s blessing to expand the emergency ferry terminals in Stumpy Point and Rodanthe.
full story »


Surfers fear loss of access to acclaimed break

Plans for the breach cut by Hurricane Irene at Mirlo Beach is making waves because surfers fear a bridge would cut off access to an acclaimed break.
full story »


Timetable set for long-term options to fix N.C. 12

The state agency will hold a pair of workshops in December for the public to comment on proposals to address the breaches formed by Hurricane Irene.
full story »


N.C. 12 reopens after construction whirlwind

Six weeks after Hurricane Irene cut two inlets across it, N.C. 12 on northern Hatteras Island reopened Monday.
full story »


N.C. 12 to reopen by Tuesday, NCDOT says

N.C. 12, closed since the end of August, will reopen no later than Oct. 11 with a new bridge over an inlet created by Hurricane Irene, the North Carolina Department of Transportation says.
full story »


N.C. 12 update: Target for re-opening is Oct. 15

Construction crews have reached another milestone with the installation of all 82 pilings that will support a temporary bridge over the mid-Pea Island breach.
full story »


Pea Island breach is 6 to 8 feet deep, 200 feet wide

Boats that try to navigate the breach will likely be limited by the water depth and conditions, and the Coast Guard has not issued any notices yet.
full story »


Paving starts at Mirlo; N.C. 12 bridge taking shape

Crews have finished the bulkheading for the north and south shore landings of a temporary two-lane bridge over the breach in the Pea Island National Wildlife Refuge.
full story »


Bryant says refuge on board with road repairs

The head of the Pea Island National Wildlife Refuge seeks to dispel talk that the U.S. Fish and Wildlife Service is slowing down N.C. 12 repairs.
full story »


Commissioners stand by decision to open Hatteras

Answering criticism from tourism and business leaders, commissioners say they made the right decision in reopening lower Hatteras Island.
full story »